Inside Overhaul
![Before - Full Basement finish. We moved the wall back a foot as you come down to create a larger opening.](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/277667860_5171870106193273_2269593782260068451_n/2819340841.jpg)
Before - Full Basement finish. We moved the wall back a foot as you come down to create a larger opening.
![Before - Full Basement finish. We moved the wall back a foot as you come down to create a larger opening.](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/277668705_5171870249526592_692612364378262039_n/3698485424.jpg)
Before - Full Basement finish. We moved the wall back a foot as you come down to create a larger opening.
![Before - Full Basement finish. We moved the wall back a foot as you come down to create a larger opening.](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/277666995_5171869519526665_8111979064753070990_n/1644284588.jpg)
Before - Full Basement finish. We moved the wall back a foot as you come down to create a larger opening.
![Removed 2 load bearing walls and installed new beam to create an open concept. Removed floor in old porch and installed floor joist that we raised 4 inches to make all even. Installed new tongue and groove sub floor sheeting](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/299135314_5558584784188468_7360124487374722425_n/2484888526.jpg)
Removed 2 load bearing walls and installed new beam to create an open concept. Removed floor in old porch and installed floor joist that we raised 4 inches to make all even. Installed new tongue and groove sub floor sheeting
![Removed 2 load bearing walls and installed new beam to create an open concept. Removed floor in old porch and installed floor joist that we raised 4 inches to make all even. Installed new tongue and groove sub floor sheeting](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/299148644_5558585010855112_1019514892567666822_n/732322768.jpg)
Removed 2 load bearing walls and installed new beam to create an open concept. Removed floor in old porch and installed floor joist that we raised 4 inches to make all even. Installed new tongue and groove sub floor sheeting
![Removed 2 load bearing walls and installed new beam to create an open concept. Removed floor in old porch and installed floor joist that we raised 4 inches to make all even. Installed new tongue and groove sub floor sheeting](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/299165124_5558584907521789_7418389292327898349_n/1968828061.jpg)
Removed 2 load bearing walls and installed new beam to create an open concept. Removed floor in old porch and installed floor joist that we raised 4 inches to make all even. Installed new tongue and groove sub floor sheeting
![Removed 2 load bearing walls and installed new beam to create an open concept. Removed floor in old porch and installed floor joist that we raised 4 inches to make all even. Installed new tongue and groove sub floor sheeting](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/299167843_5558584610855152_1325361228096200112_n/832710248.jpg)
Removed 2 load bearing walls and installed new beam to create an open concept. Removed floor in old porch and installed floor joist that we raised 4 inches to make all even. Installed new tongue and groove sub floor sheeting
![Removed 2 load bearing walls and installed new beam to create an open concept. Removed floor in old porch and installed floor joist that we raised 4 inches to make all even. Installed new tongue and groove sub floor sheeting](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/299179081_5558585334188413_6696361120695352365_n/2954148753.jpg)
Removed 2 load bearing walls and installed new beam to create an open concept. Removed floor in old porch and installed floor joist that we raised 4 inches to make all even. Installed new tongue and groove sub floor sheeting
![Removed 2 load bearing walls and installed new beam to create an open concept. Removed floor in old porch and installed floor joist that we raised 4 inches to make all even. Installed new tongue and groove sub floor sheeting](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/299202477_5558584150855198_8677852668996139702_n/3590466543.jpg)
Removed 2 load bearing walls and installed new beam to create an open concept. Removed floor in old porch and installed floor joist that we raised 4 inches to make all even. Installed new tongue and groove sub floor sheeting
![Removed 2 load bearing walls and installed new beam to create an open concept. Removed floor in old porch and installed floor joist that we raised 4 inches to make all even. Installed new tongue and groove sub floor sheeting](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/299307981_5558585470855066_711502839740050427_n/2093259712.jpg)
Removed 2 load bearing walls and installed new beam to create an open concept. Removed floor in old porch and installed floor joist that we raised 4 inches to make all even. Installed new tongue and groove sub floor sheeting
![BEFORE: Removed a 14ft load bearing wall. Per engineer specs, installed a 4 ply 2x12 in attic on top of trusses, screwed 5 1/2" structural screws 6" on center on both sides, installed double huricane hangers on both sides of beam to truss and fastened by using 3 1/2" sds structural screws on top and 1 1/2 into the bottom cord of the trusses. All said and done this has almost 450 structural screws in.](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/336450772_181443617989897_5720404711394093998_n/318134372.jpg)
BEFORE: Removed a 14ft load bearing wall. Per engineer specs, installed a 4 ply 2x12 in attic on top of trusses, screwed 5 1/2" structural screws 6" on center on both sides, installed double huricane hangers on both sides of beam to truss and fastened by using 3 1/2" sds structural screws on top and 1 1/2 into the bottom cord of the trusses. All said and done this has almost 450 structural screws in.
![Removed a 14ft load bearing wall. Per engineer specs, installed a 4 ply 2x12 in attic on top of trusses, screwed 5 1/2" structural screws 6" on center on both sides, installed double huricane hangers on both sides of beam to truss and fastened by using 3 1/2" sds structural screws on top and 1 1/2 into the bottom cord of the trusses. All said and done this has almost 450 structural screws in.](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/335460562_528435496154087_2713743778907336176_n/382862834.jpg)
Removed a 14ft load bearing wall. Per engineer specs, installed a 4 ply 2x12 in attic on top of trusses, screwed 5 1/2" structural screws 6" on center on both sides, installed double huricane hangers on both sides of beam to truss and fastened by using 3 1/2" sds structural screws on top and 1 1/2 into the bottom cord of the trusses. All said and done this has almost 450 structural screws in.
![Removed a 14ft load bearing wall. Per engineer specs, installed a 4 ply 2x12 in attic on top of trusses, screwed 5 1/2" structural screws 6" on center on both sides, installed double huricane hangers on both sides of beam to truss and fastened by using 3 1/2" sds structural screws on top and 1 1/2 into the bottom cord of the trusses. All said and done this has almost 450 structural screws in.](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/336158422_792794635101395_2189467735919271878_n/3043948905.jpg)
Removed a 14ft load bearing wall. Per engineer specs, installed a 4 ply 2x12 in attic on top of trusses, screwed 5 1/2" structural screws 6" on center on both sides, installed double huricane hangers on both sides of beam to truss and fastened by using 3 1/2" sds structural screws on top and 1 1/2 into the bottom cord of the trusses. All said and done this has almost 450 structural screws in.
![Removed a 14ft load bearing wall. Per engineer specs, installed a 4 ply 2x12 in attic on top of trusses, screwed 5 1/2" structural screws 6" on center on both sides, installed double huricane hangers on both sides of beam to truss and fastened by using 3 1/2" sds structural screws on top and 1 1/2 into the bottom cord of the trusses. All said and done this has almost 450 structural screws in.](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/336511804_3259337291045451_3489306988645078486_n/2905676646.jpg)
Removed a 14ft load bearing wall. Per engineer specs, installed a 4 ply 2x12 in attic on top of trusses, screwed 5 1/2" structural screws 6" on center on both sides, installed double huricane hangers on both sides of beam to truss and fastened by using 3 1/2" sds structural screws on top and 1 1/2 into the bottom cord of the trusses. All said and done this has almost 450 structural screws in.
![Removed a 14ft load bearing wall. Per engineer specs, installed a 4 ply 2x12 in attic on top of trusses, screwed 5 1/2" structural screws 6" on center on both sides, installed double huricane hangers on both sides of beam to truss and fastened by using 3 1/2" sds structural screws on top and 1 1/2 into the bottom cord of the trusses. All said and done this has almost 450 structural screws in.](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/336649495_681349877101516_4299898935019459661_n/1284600307.jpg)
Removed a 14ft load bearing wall. Per engineer specs, installed a 4 ply 2x12 in attic on top of trusses, screwed 5 1/2" structural screws 6" on center on both sides, installed double huricane hangers on both sides of beam to truss and fastened by using 3 1/2" sds structural screws on top and 1 1/2 into the bottom cord of the trusses. All said and done this has almost 450 structural screws in.
![AFTER: Removed a 14ft load bearing wall. Per engineer specs, installed a 4 ply 2x12 in attic on top of trusses, screwed 5 1/2" structural screws 6" on center on both sides, installed double huricane hangers on both sides of beam to truss and fastened by using 3 1/2" sds structural screws on top and 1 1/2 into the bottom cord of the trusses. All said and done this has almost 450 structural screws in.](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/336077593_186594390842844_896963231778047360_n/795707968.jpg)
AFTER: Removed a 14ft load bearing wall. Per engineer specs, installed a 4 ply 2x12 in attic on top of trusses, screwed 5 1/2" structural screws 6" on center on both sides, installed double huricane hangers on both sides of beam to truss and fastened by using 3 1/2" sds structural screws on top and 1 1/2 into the bottom cord of the trusses. All said and done this has almost 450 structural screws in.
![Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/after-additoin/2389160995.jpg)
Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side
![Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/befora-addition/3863802600.jpg)
Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side
![Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/during-addition-2/3420220027.jpg)
Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side
![Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/during-addition-3/4076879578.jpg)
Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side
![Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/during-addition-4/286019368.jpg)
Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side
![Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/during-addition/1615219938.jpg)
Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side
![Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/new-bathroom/1254166799.jpg)
Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side
![Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/new-deck-and-side-landing/2033774725.jpg)
Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side
![Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/new-entryway/2059787589.jpg)
Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side
![Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/new-flooring-2/4069722937.jpg)
Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side
![Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/new-flooring/1174213106.jpg)
Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side
![Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side](https://jcxconstruction.com/wp-content/uploads/cache/2022/05/vaulted-ceilings/3056437214.jpg)
Here is a 16x20 adddition we did in Nevada last year. We dug out for a 4 foot crawl space and poured a concrete wall. This one has a new master bedroom with vaulted ceilings, master bathroom and new laundry room. We removed a triple window and created an entry way to this new addition. New siding and roofing to match the house. We also buillt a new 12x20 back deck and a 3x4 landing on the side